Bloomfield-Windsor Line

 

 

 

 

 

Location: Bloomfield, CT

Description: Harlan Electric Company completed the renovation of 7.0 miles of DCT Tower Separation. Rebuild construction also included line realignment at the Rood Ave Substation in Bloomfield, Connecticut.

  • Phase 1:  1777/1779 Line Double Circuit Separation consisting of foundation, structure and wire installation for a new 1.6 mile monopole 115kV line.
  • Phase 2:  1777/1751 Line Double Circuit Separation consisting of the installation of 49 monopole structures and the transferring of 5.3 miles of existing line conductor and OPGW.
  • Phase 3:  1779 Line into Rood Avenue Substation consisting of foundation, structure and wire installation to cut the existing 1779 Line into Rood Avenue Substation.

This project was challenging due to the very stringent environmental permitting requirements along with the complex outage schedule.  The project team worked very well together in planning and executing the work in a safe and efficient manner while staying within its budget and schedule goals.

Client:   Eversource

Completion Date: 2017